RESOLVED –
(1) T H A T the Quarter 4/End of Year position of corporate risks outlined in the
Risk Summary Report (Annex A) be noted.
(2) T H A T the Strategic Leadership Team’s consideration of the responses to
the Governance and Audit Committee’s comments for Quarter 3 be noted.
(3) T H A T Cabinet be requested to approve the delegated authority for the
Director of Corporate Resources to update the Risk Management Policy.
(4) T H A T Cabinet be requested to consider the comments of the Governance
and Audit Committee as per resolutions 5 and 6.
(5) T H A T additional information be provided to the Governance and Audit
Committee relating to the Scrutiny review into Additional Learning Needs Resource
Bases.
(6) T H A T a review of the risk scoring relating to the Climate Change Risk to be
undertaken.
Reasons for decisions
(1) Following consideration of the Q4 risk update and end of year position of
corporate risks, including any emerging issues and proposed mitigations, as set out
in Annex A.
(2) To identify the actions undertaken in response to Governance and Audit
Committee’s comments and consider any further action required.
(3) The Council reviewed and approved a revised Risk Management Policy in
2024/25. Since its approval, non-material, operational amendments have been made
to reflect decisions agreed by the Governance and Audit Committee and Cabinet.
Delegated authority was requested to be granted to the Director of Corporate
Resources to make further nonmaterial, operational amendments to the Risk
Management Policy and related guidance during the year, where necessary to give
effect to decisions of the Governance and Audit Committee and Cabinet.
(4) To ensure Cabinet have oversight of resolutions relating to the Council’s Risk
Register.
(5) To ensure that Governance and Audit Committee have oversight of the
Additional Learning Needs Risk.
(6) To undertake a review of the risk score given the forecasted direction of
travel.
RESOLVED –
(1) T H A T the report findings from Audit Wales’ review of the Council’s response
to its recruitment and retention challenges, (Appendix A) and the response to the
review findings and Audit Wales’ recommendations (Appendix B) be noted.
(2) T H A T the report be referred to Cabinet for their oversight and
endorsement.
Reasons for decisions
(1) Having regard to the contents of the report and discussions at the meeting.
(2) To enable Cabinet’s oversight and endorsement.
RESOLVED –
(1) T H A T the contents of the report be noted.
(2) T H A T the response letter from the then Welsh Government Cabinet
Secretary for Housing and Local Government (Appendix C), concerning the financial
impact of the Homelessness and Social Housing Allocation (Wales) Act 2026, be
noted.
Reasons for decisions
(1) To advise the Governance and Audit Committee of progress in relation to its
decisions and actions requested.
(2) To advise the Governance and Audit Committee of the response received
from the then Welsh Government Cabinet Secretary for Housing and Local
Government.
RESOLVED –
(1) T H A T the progress in addressing external regulatory recommendations as
detailed in the appended Strategic Insight Board Insight Tracker for the period Q4
2025/26 be noted.
(2) T H A T Cabinet be requested to endorse the removal of completed actions
from the Insight Tracker.
(3) T H A T the Director of Corporate Resources considers providing future
iterations of the Quarter position earlier to the Governance and Audit Committee.
Reason for decision
(1) To ensure regulatory recommendations were appropriately considered.
(2) To ensure that the Council's Strategic Insight Board Insight Tracker reflected
the Council’s most up to date position on its regulatory recommendations.
(3) To ensure that Governance and Audit Committee receive more timely
updates.
RESOLVED – T H A T the outcome of the self-assessment of the effectiveness of
the Governance and Audit Committee be noted.
Reason for decision
To provide assurance that the Council’s Governance and Audit Committee could
demonstrate its effectiveness against the good practice principles set by the
Chartered Institute of Public Finance and Accountancy (CIPFA) using the self-
assessment tools provided.
RESOLVED:
To note the Quarter 1 Progress Update including the Corporate Parenting
Quarterly Progress Report Quarter 1 2026-27 and note the observations
and comments for inclusion in the plan.
RESOLVED – T H A T the minutes of the meeting held on 21st May 2026 be
approved as a correct record.
BUILDING REGULATION APPLICATIONS AND OTHER BUILDING CONTROL MATTERS DETERMINED BY THE HEAD OF SUSTAINABLE DEVELOPMENT UNDER DELEGATED POWERS (HSD)
RESOLVED –
(1) T H A T the passed building regulation applications, as listed in Section (a) of
the report, be noted.
(2) T H A T the rejected building applications, as listed in Section (b) of the report,
be noted.
(3) T H A T the serving of Notices under Building (Approved Inspectors Etc.)
Regulations 2000, as listed in Section (c) of the report, be noted.
(4) T H A T Section 32 of the Building Act, 1984 be implemented in order to serve
notices in respect of plans which are three or more years old and that the serving of
such notices, as listed in Section (d) of the report, be noted.
PLANNING APPLICATIONS DETERMINED BY THE HEAD OF SUSTAINABLE DEVELOPMENT UNDER DELEGATED POWERS (HSD)
RESOLVED – T H A T the applications as outlined within the report, on pages 8
through 16, under the above delegated powers, be noted.
TREES (HSD)
(i) Delegated Powers –
RESOLVED – T H A T the applications as outlined within the report, on pages 17
and 18, as determined by the Head of Sustainable Development under delegated
powers, be noted.
FOR INFORMATION ONLY PLANNING REPORT: BERTH 31, WIMBORNE ROAD, BARRY (HDS)
RESOLVED – T H A T the report be noted.
Reason for decision
Having regard to the contents to the report.
PLANNING APPLICATIONS (HSD)
RESOLVED – T H A T in pursuance of the powers delegated to the Committee, the
following applications be determined as indicated and any other necessary action be
taken.
2025/01139/FUL Received on 14 November 2025
(P. 23)
APPLICANT: Morris Commercial Ltd C/o Agent
AGENT: Max Lewis Brunel House, 2 Fitzalan Road, Cardiff, CF24 0EB
Hangar 858, Bro Tathan North, St Athan
The change of use of an existing aircraft hangar (Class B8) to a facility for the
assembly of electric vehicles (Class B2), demolition of existing extensions, external
alterations, vehicle parking, drainage connection, servicing and all associated
building and engineering works.
The application was required to be determined by Planning Committee under the
Council’s approved scheme of delegation because the application had been called in
for determination by Councillor Haines for the reason owing to traffic and lighting
concerns raised.
APPROVED subject to the following condition(s):
1. The development shall begin no later than five years from the date of this
decision.
Reason:
To comply with the requirements of Section 91 of the Town and Country
Planning Act 1990.
2. The development shall be carried out in accordance with the following
approved plans and documents:
1034 02 Site Location Plan
1034 30 Proposed Ground Floor Plan
1034 31 Proposed First Floor Plan
1034 34 Proposed Second Floor Plan
1034 25 Proposed North South Elevation
1034 26 Proposed North East Elevation
1034 27 Proposed South West Elevation
1034 107 Proposed Hardstand
1034 106 Proposed Fencing
1034 105 Proposed Site Plan
1034 103 Proposed App Site
51044 Proposed Drainage Ga 1
10502 Proposed Drainage Ga 2 of 3
10503 Proposed Drainage Ga 3
Proposed Site Plan Lighting
Lighting Impact Assessment Unit 858
Ecological Assessment (David Clements Ecology Ltd, August 2025)
Battery Safety Management Plan Oct 25 V2B
Reason:
For the avoidance of doubt as to the approved development and to accord
with Circular 016:2014 on The Use of Planning Conditions for Development
Management.
3. Prior to the first beneficial use of the development, a Biodiversity
Enhancement Strategy addressing enhancement measures shall be
submitted to and approved in writing by the Local Planning Authority. The
development shall thereafter be carried out in accordance with the approved
strategy and timings set out within and thereafter retained in accordance with
the approved details whilst the development remains in existence. The
Strategy shall include the following:
a) Replacement nesting sites for jackdaw
b) Replacement roosting site for barn owl
c) Site clearance strategy
d) Surrounding grassland management (particularly with respect to Great
Crested Newt- the NLMS)
e) Details of the water-carrying capacity of the attenuation pond
Reason:
In the interests of ecology and to ensure compliance with Policies SP1
(Delivering the Strategy) and MD9 (Promoting Biodiversity) of the Local
Development Plan.
4. Notwithstanding the provisions of the Town and Country Planning (Use
Classes) Order 1987, the buildings hereby approved shall be restricted to
uses falling within Use Class B2 or B8 only of the schedule of the Town and
Country Planning (Use Classes) Order 1987, or in any provision equivalent to
that Class in any statutory instrument amending, revoking or re-enacting that
Order.
Reason: To control the precise nature of the use of the building given its
location within an allocated employment site, and to ensure compliance with
the terms of Policies MD1 and MD2 of the Local Development Plan.
5. Deliveries shall not be taken at or dispatched from the site outside the hours
of 08:00 to 22:00 Monday to Friday, 08:00 to 22:00 on Saturdays and 08:00 to
22:00 on Sundays.
Reason:
To ensure the safeguarding the amenity of residential properties, and to
ensure compliance with the terms of Policies SP1 (Delivering the Strategy),
MD2 (Design of New Developments) and MD7 (Environmental Protection) of
the Local Development Plan.
6. The external lighting scheme shall be carried out in accordance with the
approved Lighting Impact Assessment and associated lighting drawings. No
additional external lighting, or alterations to the approved lighting scheme,
shall be installed.
Reason:
To safeguard residential amenity in accordance with Policies SP1 (Delivering
the Strategy) and MD2 (Design of New Development) of the Vale of
Glamorgan Local Development Plan 2011-2026.
7. No development shall commence until details of a scheme to provide for the
provision of a demarcated pedestrian/cycle route within the existing
carriageway connecting the site to the Northern Access Road have been
submitted to and approved in writing by the Local Planning Authority. The
scheme shall include full details of layout, dimensions, surfacing,
lining/markings and signage.
The approved scheme shall be implemented in full prior to the first use of the
development and shall thereafter be retained unless and until a permanent
alternative active travel route serving the site has been provided in
accordance with a separate planning permission or agreed scheme.
Reason:
In the interests of pedestrian and cyclist safety, accessibility and the
promotion of sustainable travel, to ensure compliance with Policy MD2
(Design of New Development) of the Vale of Glamorgan Local Development
Plan 2011-2026 and Planning Policy Wales.
8. Notwithstanding the details submitted, any boundary fence or enclosure along
the remaining site frontage shall be setback to a minimum of 4 metres from
the highway boundary. This setback shall be retained free of obstruction to
facilitate the potential future provision of an Active Travel Route serving the
site in accordance with a separate planning permission or agreed scheme.
Reason:
In the interests of pedestrian and cyclist safety, accessibility and the
promotion of sustainable travel, to ensure compliance with Policy MD2
(Design of New Development) of the Vale of Glamorgan Local Development
Plan 2011-2026 and Planning Policy Wales.
9. The turning area indicated on the approved swept path drawings for
articulated vehicles shall be clearly demarcated (including hatching) and
retained solely for the turning and manoeuvring of vehicles. The area shall not
be used for parking at any time.
Reason:
In the interests of pedestrian and cyclist safety, accessibility and the
promotion of sustainable travel, to ensure compliance with Policy MD2
(Design of New Development) of the Vale of Glamorgan Local Development
Plan 2011-2026 and Planning Policy Wales.
10. The drainage scheme for the site shall ensure that all foul and surface water
discharges separately from the site and that land drainage run-off shall not
discharge, either directly or indirectly, into the public sewerage system.
Reason:
To prevent hydraulic overloading of the public sewerage system, pollution of
the environment and to protect the health and safety of existing residents and
ensure no detriment to the environment and to comply with the terms of Policy
/ Policies SP1 (Delivering the Strategy) / MD1 (Location of New Development)
of the Local Development Plan.
11. No development on the site shall commence until the following components of
a scheme to deal with the risks associated with contamination at the site, has
been submitted to and approved in writing by the Local Planning Authority.
2. A site investigation scheme, based on previous site uses, potential
contaminants, the site conceptual model, and any associated risks to provide
information for a detailed assessment of the risk to all receptors that may be
affected, including those off site.
3. The results of the site investigation and the detailed risk assessment
referred to in (2) and, based on these, an options appraisal and remediation
strategy giving full details of the remediation measures required and how they
are to be undertaken.
4. A verification plan providing details of the data that will be collected in order
to demonstrate that the works set out in the remediation strategy in (3) are
complete and identifying any requirements for longer-term monitoring of
pollutant linkages, maintenance, and arrangements for contingency action.
The remediation strategy and its relevant components shall be carried out in
accordance with the approved details.
Reason:
To ensure the risks associated with contamination at the site have been fully
considered prior to commencement of development as controlled waters are
of high environmental sensitivity; and where necessary remediation measures
and long-term monitoring are implemented to prevent unacceptable risks from
contamination and to ensure compliance with Policy MD7 (Environmental
Protection) of the adopted Local Development Plan.
12. Prior to the occupation of the development a verification report demonstrating
completion of works set out in the approved remediation strategy and the
effectiveness of the remediation shall be submitted to and approved in writing
by the Local Planning Authority. The report shall include results of sampling
and monitoring carried out in accordance with the approved verification plan to
demonstrate that the site remediation criteria have been met. It shall also
include a long-term monitoring and maintenance plan for longer-term
monitoring of pollutant linkages, maintenance, and arrangements for
contingency action, as identified in the verification plan. The long-term
monitoring and maintenance plan shall be carried out in accordance with the
approved details.
Reason:
To ensure the methods identified in the verification plan have been
implemented and completed and the risk associated with the contamination at
the site has been remediated prior to occupation or operation, to prevent both
future users of the land and neighbouring land are minimised, together with
those to controlled waters, property and ecological systems, and to ensure
that the development can be carried out safely without unacceptable risks to
workers, neighbours and other offsite receptors and to ensure compliance
with the provisions of MD7 of the adopted Local Development Plan.
13. If, during development, contamination not previously identified is found to be
present at the site then no further development (unless otherwise agreed in
writing with the Local Planning Authority) shall be carried out until a
remediation strategy detailing how this unsuspected contamination shall be
dealt with has been submitted to and approved in writing by the Local
Planning Authority. The remediation strategy shall be carried out as approved.
Reason
To ensure the risks associated with previously unsuspected contamination at
the site are dealt with through a remediation strategy, to minimise the risk to
both future users of the land and neighbouring land, and to ensure that the
development can be carried out safely without unacceptable risks and to
ensure compliance with the provisions of MD7 of the adopted Local
Development Plan.
14. Piling or any other foundation designs using penetrative methods shall not be
permitted other than with the express written consent of the Local Planning
Authority, which may be given for those parts of the site where it has been
demonstrated that there is no resultant unacceptable risk to groundwater. The
development shall be carried out in accordance with the approved details.
Reason:
In order to ensure the amenities of nearby occupiers is protected and to
ensure accordance with Policies SP1 (Delivering the Strategy) / MD2 (Design
of New Developments) and MD7 (Environmental Protection) of the Local
Development Plan.
15. No infiltration of surface water drainage into the ground is permitted other than
with the express written consent of the local planning authority, which may be
given for those parts of the site where it has been demonstrated that there is
no resultant unacceptable risk to controlled waters. The development shall be
carried out in accordance with the approved details.
Reason: To prevent both new and existing development from contributing to
or being put at unacceptable risk from or being adversely affected by
unacceptable levels of water pollution and to ensure compliance with the
provisions of Policy MD7 of the adopted Local Development Plan.
16. Any topsoil [natural or manufactured] or subsoil, to be imported shall be
assessed for chemical or other potential contaminants in accordance with a
scheme of investigation which shall be submitted to and approved in writing
by the Local Planning Authority in advance of its importation. Only material
approved by the Local Planning Authority shall be imported. All measures
specified in the approved scheme shall be undertaken in accordance with
Pollution Control’s Imported Materials Guidance Notes. Subject to approval of
the above, sampling of the material received at the development site to verify
that the imported soil is free from contamination shall be undertaken in
accordance with a scheme and timescale to be agreed in writing by the LPA.
Reason:
To ensure that the safety of future occupiers is not prejudiced in accordance
with Policy / Policies SP1 (Delivering the Strategy) / MD7 (Environmental
Protection) of the Local Development Plan.
17. Any aggregate (other than virgin quarry stone) or recycled aggregate material
to be imported shall be assessed for chemical or other potential contaminants
in accordance with a scheme of investigation which shall be submitted to and
approved in writing by the Local Planning Authority in advance of its
importation. Only material approved by the Local Planning Authority shall be
imported. All measures specified in the approved scheme shall be undertaken
in accordance with Pollution Control’s Imported Materials Guidance Notes.
Subject to approval of the above, sampling of the material received at the
development site to verify that the imported soil is free from contamination
shall be undertaken in accordance with a scheme and timescale to be agreed
in writing by the LPA.
Reason:
To ensure that the safety of future occupiers is not prejudiced in accordance
with Policy / Policies SP1 (Delivering the Strategy) / MD7 (Environmental
Protection) of the Local Development Plan.
18. No development shall take place until the applicant, or their agents or
successors in title, has secured implementation of a programme of
archaeological work in accordance with that out-lined in “Picketstone, Bro
Tathan, Vale of Glamorgan: Written Scheme of Investigation for Historic
Building Recording of part of Building 858 and Attenuation pond
archaeological watching brief (Heneb The Trust for Welsh Archaeology
Glamorgan Gwent Archaeology, dated August 2025, reference 2025/031).
Reason:
In order that archaeological operations are undertaken to an
acceptable standard and that legitimate archaeological interest in the
site is satisfied and to ensure compliance with Policies SP1 (Delivering
the Strategy), SP10 (Built and Natural Environment) and MD8 (Historic
Environment) of the Local Development Plan.
Reason for decision
The decision to recommend planning permission has been taken in accordance with
Section 38 of The Planning and Compulsory Purchase Act 2004, which requires that,
in determining a planning application the determination must be in accordance with
the Development Plan unless material considerations indicate otherwise. The
Development Plan for the area comprises the Vale of Glamorgan Adopted Local
Development Plan 2011-2026 and Future Wales – the National Plan 2040.
Having regard to Policies SP1 – Delivering the Strategy, MG9 – Employment
Allocations, MD2 - Design of New Development, MD7 - Environmental Protection,
MD16 - Protection of existing Employment Sites and Premises of the Adopted Local
Development Plan 2011-2026, it is considered that the proposal is acceptable in
relation to the principle of development, siting, scale, design and materials, access
and parking, impact on residential amenity and neighbouring units, flooding and
drainage and ecology.
Having regard to the Council’s duties under the Equality Act 2010 the proposed
development does not have any significant implications for, or effect on, persons
who share a protected characteristic.
It is considered that the decision complies with the Council’s well-being objectives
and the sustainable development principle in accordance with the requirements of
the Well-being of Future Generations (Wales) Act 2015.
The appropriate marine policy documents have been considered in the determination
of this application in accordance with Section 59 of the Marine and Coastal Access
Act 2009.
2024/00534/FUL Received on 3 November 2025
(P. 57)
APPLICANT: Kimberley Danter The Boat House, Symonds Yat, HR9 6BZ
AGENT: Laurence Clarke 6 Grove Place, Penarth, CF64 2ND
Land on Hayes Road, Sully.
Approximately 2.5 hectares of vehicle and container storage, with approximately 1.2
hectares of rewilding and planting in the southwest of the site and along the
boundary.
The application was required to be determined by Planning Committee under the
Council’s approved scheme of delegation because the application was of a scale
and / or nature that was not covered by the scheme of delegation.
REFUSED
1. Given the sparse layout and the limited employment being provided by the
development (up to one full time and one part time employee), the
development is considered an inefficient use of allocated employment land
and is therefore contrary to the aims of Policies MG9 (Employment
Allocations) and MD15 (Protection of Allocated Employment Sites) of the Vale
of Glamorgan Adopted Local Development Plan (2011 - 2026).
2. Insufficient information has been submitted, including the submission of
accurate ground levels, to demonstrate that the proposed development would
not have an unacceptable impact on the visual amenity of the site and
surroundings and therefore the scheme as submitted is considered to conflict
with Policy MD2 (Design of New Development) of the Vale of Glamorgan
Adopted Local Development Plan (2011-2026).
3. The application site has been subjected to a significant loss of vegetation, and
the Green Infrastructure Statement has failed to demonstrate that the step-
wise approach as set out in Chapter 6 of Planning Policy Wales (Edition 12)
has been followed. Whilst the loss of trees and vegetation is irreversible,
insufficient information has been submitted to provide a baseline for the
previous state of the site, as well as a survey of existing mature trees and
vegetation together with a preliminary ecological assessment, to demonstrate
that the proposals would have an acceptable impact on existing trees and the
ecological value of the site. It has therefore not been demonstrated that the
proposals would secure a net benefit in terms of biodiversity and the
development is therefore considered contrary to Policies MG19 (Sites and
Species of European Importance), MG20 (Nationally Protected Sites and
Species) and MD9 (Promoting Biodiversity) of the Vale of Glamorgan Adopted
Local Development Plan (2011-2026), as well as Chapter 6 of Planning Policy
Wales (Edition 12), and the Council's Supplementary Planning Guidance on
Trees, Woodland, Hedgerows and Development (2025) and Biodiversity and
Development (2018).
4. Insufficient information has been provided to demonstrate that the proposals
would have an acceptable impact on highway safety, including the omission of
swept paths, which are required to demonstrate that the junction with Hayes
Road would operate safely and that the site could be safely navigated by
HGVs. A turning area has also not been provided within the site, to ensure
vehicles can exit in a forward gear and it has also not been demonstrated that
the internal roads would maintain a width of 7.3m and incorporate pedestrian
facilities. The application also lacks a transport statement to assess the
impact of additional trips to the site on the highway network and engineering
drawing detailing the proposed new access arrangement has also not been
provided. As such, the proposals are considered contrary to criterion 6 of
Policy MD2 of the Vale of Glamorgan Adopted Local Development Plan
(2011-2026).
5. Insufficient information has been provided to demonstrate that the proposal
would adequately protect the amenity of neighbouring occupiers, in particular
how noise impacts would be mitigated to safeguard the amenity of adjoining
sensitive residential uses. The proposal therefore fails to demonstrate
compliance with criteria 8 of Policy MD2 (Design of New Development) of the
Vale of Glamorgan Adopted Local Development Plan (2011-2026).
Reason for decision
The decision to refuse planning permission has been taken in accordance with
Section 38 of The Planning and Compulsory Purchase Act 2004, which requires that,
in determining a planning application the determination must be in accordance with
the Development Plan unless material considerations indicate otherwise. The
Development Plan for the area comprises the Vale of Glamorgan Adopted Local
Development Plan 2011-2026 and Future Wales – the National Plan 2040.
Having regard to the Council’s duties under the Equality Act 2010 the proposed
development does not have any significant implications for, or effect on, persons
who share a protected characteristic.
It is considered that the decision complies with the Council’s well-being objectives
and the sustainable development principle in accordance with the requirements of
the Well-being of Future Generations (Wales) Act 2015.
The appropriate marine policy documents have been considered in the determination
of this application in accordance with Section 59 of the Marine and Coastal Access
Act 2009.
Penderfyniad: Argymhellodd y Cabinet y dylai'r Cyngor gymeradwyo pedwar peth: yr Adroddiad Blynyddol 2025-26 cyn ei gyhoeddi; y polisi Caerdydd Ddwyieithog, Cyngor Dwyieithog diwygiedig, i'w gyhoeddi ar fewnrwyd y Cyngor; Asesiad Effaith Sengl y polisi hwnnw; a'r Canllawiau diwygiedig ar Ymdrin â Galwadau Cymraeg. Nid y Cabinet sy'n rhoi'r cymeradwyaeth derfynol yma. Y Cyngor sy'n penderfynu.
Penderfyniad: Cymeradwyodd y Cabinet ddechrau tendr cystadleuol ar gyfer Cam 1a, gan ddefnyddio Fframwaith Priffyrdd De-ddwyrain Cymru (Lot 9) a hysbysiad ar Sell2Wales. Cymeradwyodd sgorio tendrau ar sail 60% cost, 30% ansawdd a 10% gwerth cymdeithasol. Dirprwyodd y gwaith o ddyfarnu'r contract, a'r camau i ddechrau a chyflawni'r gwaith, i'r Cyfarwyddwr Cynorthwyol Cynllunio a Thrafnidiaeth, ar ôl ymgynghori ag Aelod y Cabinet dros Newid yn yr Hinsawdd, Cynllunio Strategol a Thrafnidiaeth, Swyddog Adran 151 (y swyddog sy'n gyfrifol am gyllid y Cyngor) a'r Cyfarwyddwr Llywodraethu a Gwasanaethau Cyfreithiol. Nododd y bydd y Cyfarwyddwr Cynorthwyol yn gweithredu fel Uwch Berchennog Cyfrifol, yn atebol am gyflawni nodau a manteision y prosiect.
Penderfyniad: Nododd y Cabinet yr adroddiad a'r camau a gymerwyd ar sefyllfa alldro refeniw a chyfalaf y Cyngor (ei sefyllfa wario derfynol ar ddiwedd y flwyddyn) ar gyfer 2025/26. Nododd hefyd y bydd yr adroddiad yn atodiad i'r adroddiad Datganiadau Ariannol ar gyfer cyfarfod o'r Cyngor yn hydref 2026.
RESOLVED: To note the Terms of Reference for the Appointment Committee.
To discharge the functions of the authority in respect of the appointment and dismissal of Chief Officers and Deputy Chief Officers (as defined in the Local Authorities (Standing Orders) (Wales) Regulations 2006) and the statutory Head of Democratic Services, in accordance with the Employment Procedure Rules and other relevant Council policies and procedures.
RESOLVED: That the public be excluded during the discussion on the following item of business on the grounds that, if members of the public were present during the discussion, because of the nature of the business to be transacted there would be disclosure to them of the exempt information as defined in Part 4 of Schedule 12A of the Local Government Act 1972 and as described below:
Paragraph 12 – Information relating to an applicant to become an employee of the Authority; and
Paragraph 13 – Information which was likely to reveal the identity of an individual.
RESOLVED – That the Sub Committee, having considered the application on its individual merits, the committee papers, the Licensing Act 2003, the Section 182 guidance, the council’s Statement of Licensing Policy, submissions made by the applicant and all other parties, and the oral evidence given by the applicant and objectors during the hearing in its determination of the matter, REFUSED the application.
Members noted that the applicant demonstrated a significant lack of understanding of the licensing objectives and the legal requirements of the licensing regime. In particular, the applicant was unable to explain the licensing objectives when asked and provided inconsistent information regarding the operating hours of the premises. In particular, the applicant initially suggested that the premises had previously operated until 3am, which was later clarified as incorrect following advice from the Licensing Officer, and subsequently revised again during the hearing. The Sub Committee considered that this inconsistency reduced the weight that could be attached to the applicant’s evidence.
Members further noted that the applicant was unable to provide clear or detailed explanations as to how the licensing objectives would be promoted. In particular, limited detail was provided in relation to staff training, with reliance placed on unspecified training to be delivered by a franchisor, without any clear understanding of its content or implementation. There was insufficient evidence of measures to manage customers during late night hours, including how difficult or intoxicated individuals would be dealt with. No robust dispersal policy or noise management measures were outlined, despite the premises seeking to operate until the early hours of the morning. The Sub Committee also found that the applicant did not demonstrate an understanding of the risks associated with late-night operation in a busy and densely populated area.
The Sub Committee took into account the representations of the Ward Member, who highlighted existing issues on Crwys Road relating to noise, anti-social behaviour, and crime, particularly during late night hours. It was noted that the road already contained a substantial number of licensed premises and that residents had raised complaints about disturbance, waste management, and sleep disruption. The Sub Committee considered that the introduction of an additional premises operating until 3am was likely to add to the potential for noise and disturbance in the area, particularly in the absence of robust control measures.
Whilst the Sub Committee acknowledged the applicant’s submission that the premises had not previously been the source of complaints, it gave this limited weight given that the premises had not been operating under a premises licence permitting late-night refreshment beyond 11pm.
The Sub Committee also gave weight to the fact that this was the applicant’s first experience of the licensing process. However, this did not outweigh the concerns regarding the lack of understanding and the absence of appropriate safeguards.
Having carefully considered all of the evidence, the Sub Committee was not satisfied that the applicant had demonstrated that the licensing objectives would be promoted. In particular, the Sub Committee found that granting the application would be likely to undermine the prevention of crime and disorder and the prevention of public nuisance, having regard to the nature of the area, the proposed hours, and the lack of adequate control measures.
The Sub Committee resolved to refuse the application.
RESOLVED – T H A T the draft Statement of Licensing Policy be approved and the
Policy referred to Cabinet and Full Council for final approval.
Reason for decision
To ensure that the Licensing Authority fulfilled its duty under the Licensing Act 2003.
RESOLVED – T H A T having regard to the report, the Guidelines adopted by the
Public Protection Licensing Committee and the representations made by the
Applicant, Members determined that the Applicant was not a fit and proper person to
hold a hackney carriage and private hire vehicle driver’s licence.
Reason for decision
Members found that there was insufficient information provided to them to constitute
grounds for departing from the adopted guidelines on determining the suitability of
applicants.
Penderfyniad: Cytunodd y Pwyllgor y bydd y Cadeirydd yn ysgrifennu at Aelod y Cabinet, ar ran y Pwyllgor, gyda'i sylwadau a'i argymhellion. Cafodd y cyhoedd ei wahardd o ran o'r eitem am fod y Pwyllgor wedi trafod gwybodaeth eithriedig, sef gwybodaeth y mae'r gyfraith yn caniatáu ei chadw'n breifat.
Penderfyniad: Nododd y Pwyllgor y dull o ddatblygu ei raglen waith ar gyfer 2026-27, ac y bydd fersiwn derfynol yn dod yn ôl i'w chymeradwyo'n ffurfiol. Nododd hefyd amserlen dyddiadau'r pwyllgor.
Penderfyniad: Cymeradwyodd y Pwyllgor y newidiadau llywodraethu arfaethedig, gyda'i ddiwygiadau ei hun. Y prif bwyntiau yw: (1) Bydd swyddogion yn penderfynu ar geisiadau i amrywio amodau, gwneud newidiadau bach, cyflawni amodau neu gymeradwyo materion a gadwyd yn ôl (manylion a adawyd tan yn ddiweddarach), oni bai bod y Pwyllgor yn gofyn yn ffurfiol i un ddychwelyd ato. (2) Bydd ceisiadau'n mynd at y Pwyllgor os ydynt ar gyfer 250 neu fwy o gartrefi, mwy na 2,500 metr sgwâr o ofod masnachol, safleoedd dros 10 hectar, neu ddatblygiadau mawr gyda Datganiad Effaith Amgylcheddol. (3) Y Cadeirydd fydd yn penderfynu ar geisiadau gan aelodau i gyfeirio cais, a rhaid iddo gadw cofnod o'r penderfyniadau a'r rhesymau a'i adrodd yn rheolaidd i'r Pwyllgor. (4) Gall y Cadeirydd ofyn i gais ddod at y Pwyllgor. (5) Ymgynghorir â'r Cadeirydd pan fo pum gwrthwynebiad neu fwy yn dod o bum aelwyd neu fwy. (6) Bydd pob cais gan swyddogion yn y Gwasanaeth Cynllunio sy'n gwneud penderfyniadau cynllunio yn mynd at y Pwyllgor. Caiff pob siaradwr 4 munud, a gall mwy nag un aelod ward siarad yn ôl disgresiwn y Cadeirydd. (10) Paratoir Cod Ymarfer Da Cynllunio i Aelodau wedi'i ddiweddaru a Chanllaw Cynllunio unigol. O ran deisebau, pleidleisiodd y Pwyllgor i argymell i'r Cabinet na ddylai deisebau â 50 neu fwy o lofnodion anfon cais at y Pwyllgor yn awtomatig mwyach. Yn hytrach, byddent yn mynd at y Pennaeth Cynllunio, mewn ymgynghoriad â'r Cadeirydd, a byddai'r Cynllun Deisebau yn eithrio ceisiadau dilynol neu dechnegol. Rhoddwyd awdurdod dirprwyedig i swyddogion gwblhau'r gwelliannau i'r Cyfansoddiad, sy'n mynd at y Pwyllgor Cyfansoddiad ac yna'r Cyngor llawn. Mae newidiadau'r Cynllun Deisebau yn mynd at y Pwyllgor Cyfansoddiad ac yna'r Cabinet. Rhoddwyd awdurdod i'r Pennaeth Cynllunio gwblhau'r nodiadau gweithdrefn a'r protocolau eraill. Anfonir cadarnhad o'r trefniadau terfynol at bob aelod.
RESOLVED that the public be excluded for the following items of business as they contain exempt information by virtue of Paragraph 12 and 21 of Parts 4 and 5 of the Local Government Act 1972.
RESOLVED – That the Council be recommended to approve the recommendations of the Panel to appoint the following persons to current Local Authority Governing Body vacancies as follows:
School Name
Ward
Start of Vacancy
Applications
Received
Cantonian
Fairwater
11/04/2026
Eastern High
Trowbridge
06/05/2026
Dylan Rees
Fairwater Primary School
Fairwater
26/03/2026
Tomos Dillon
Grangetown Nursery School
Grangetown
27/03/2026
Greenhill School
Rhiwbina
02/07/2025
Hywel Dda Primary School
Ely
03/09/2025
Russell Meade
Llanedeyrn Primary School
Pentwyn
30/04/2026
Meadowbank School
Llandaff North
23/04/2026
Russell Melbourne
Marlborough Primary School
Penylan
01/05/2025
Ninian Park Primary School
Grangetown
25/04/2026
Davina Guignard
Radnor Primary School
Canton
12/12/2025
Matthew Russell
St Alban’s RC Primary School
Splott
06/02/2026
Charlotte Husnjak
St Francis RC Primary School
Ely
08/03/2025
St Joseph's R.C Primary School
Gabalfa
27/04/206
St Peters RC Primary School
Plasnewydd
30/04/2026
Michelle Matthews
The Saints Federation
Pentwyn
09/09/2025
Lee Davies
Ysgol Cynefin
East- Llanrumney
West-Fairwater
01/05/2026
Whitchurch Primary School
Whitchurch & Tongwynlais
28/10/2025
Abigail Monk-Jones
Ysgol Gyfun Gymraeg Glantaf
Llandaff North
01/05/2025
Owain Jones
Ysgol Gyfun Gymraeg Plasmawr
Fairwater
08/12/2025
Zoe Hayne
Ysgol Gymraeg Pwll Coch
Canton
30/06/2025
Gareth Jones
Ysgol Gynradd Groes-Wen Primary School
Pentyrch & St Fagans
01/02/2025
Gareth Howells
Ysgol Pencae
Llandaff
27/11/2024
The Committee received and considered applications to future vacancies against criteria, matching skills to vacancies.
RESOLVED – That the Council be recommended to approve the recommendations of the Panel to appoint the following:
School Name
Ward
Start of Vacancy
Re-appointment requested.
New Application Received
Baden Powell Primary School
Splott
28/09/2026
Stuart Parsons
Bryn Celyn Primary School
Pentwyn
28/09/2026
Cantonian High
01/07/2026
School
Fairwater
01/07/2026
Corpus Christi R.C. High School
Lisvane & Thornhill
17/09/2026
Kath Brown
30/09/2026
Gordan Plant
Eastern High x 2
Trowbridge
30/09/2026
Martin Weinel
Gabalfa Primary School
Llandaff North
30/09/2026
Thomas Wooley
Lakeside Primary School
Cyncoed
01/07/2026
Llanederyn Primary School
23/07/2026
Nicola Whitefield
Llanishen High School
Llanishen
30/09/2026
Barbara Cooke
Stephen Hudson
30/09/2026
Llysfaen Primary School
Lisvane & Thornhill
01/07/2026
Cllr Sian Melbourne
Marlborough Primary School
Penylan
01/07/2026
Andrew Twyman
Meadowlane
Primary School
Trowbridge
31/07/2026
Moorland Primary School
Splott
30/09/2026
Cllr Margaret Lewis
Pentrebane
28/09/2026
Primary School
Fairwater
30/09/2026
Peter Lea Primary School
Fairwater
01/07/2026
Radyr Primary School
Radyr &
Morganstown
28/09/2026
Rhiwbeina Primary School
Rhiwbina
30/09/2026
Dr Samuel Williams
Roath Park Primary
23/07/2026
Cllr Peter Wong
School
Plasnewydd
30/09/2026
Springwood Primary School
Pentwyn
20/07/2026
Caerdydd, Community & Adult Services Scrutiny Committee,
Penderfyniad: Cytunodd y Pwyllgor y bydd y Cadeirydd, ar ran y Pwyllgor, yn ysgrifennu at yr Aelod Cabinet gydag arsylwadau'r Pwyllgor o'r drafodaeth ar y ffordd ymlaen.