Councils decide planning applications for new buildings, extensions and changes of use, and write the local development plan that says where new homes and jobs can go. National parks decide applications inside their boundaries.
Who decides
Planning officers decide most applications. Larger or disputed ones go to the planning committee of councillors, which meets in public.
Having a say
Anyone can comment on an application while it's open, usually for 21 days. Stick to planning matters such as traffic, design, noise and overlooking.
In numbers
Welsh councils plan to spend £40 per person on this in 2026-27.
It ranges from £13 in Pembrokeshire to £152 in Neath Port Talbot.
Planning applications decided within eight weeks: 42% across Wales.
RESOLVED: Pursuant to this Committee’s delegated powers the following development control applications be determined in accordance with the recommendation set out in the reports of the Director of Planning, Transport and Environment, subject to any further amendments as detailed below and notification be given of the decisions in accordance with Section 70 of the Town and Country Planning Act 1990 or Section 74 of the Planning (Listed Building & Conservation) Act 1990.
APPLICATIONS RESOLVED TO BE GRANTED SUBJECT TO ENTERING INTO A BINDING SECTION 106 AGREEMENT
(Councillor Irene Humphreys left the meeting during consideration of this application in accordance with her prejudicial interest)
22/02184/OUT – CAERAU
LAND TO THE SOUTH WET OF PARK VIEW HEALTH CENTRE ADJACENT TO ELY AND CAERAU COMMUNITY HUB, TRESEDER WAY, CAERAU
Proposed Health and Wellbeing Hub and associated infrastructure works relating to access, parking, drainage and landscape.
Subject to the following amendment to Condition 9:
The existing children's playground shall not be removed (and shall remain available at all times for children's play) until such time as details of the relocated playground have been submitted to and improved in writing with the Local Planning Authority, and the replacement playground provided on site in accordance with the approved details. The details shall include, but not limited to the following: Location of the new playground, full details of the design and layout of the children's playground (including proposed play equipment) and natural play features, timetable for installation of playground and natural play areas, post installation inspections and maintenance by the developer before handover to the council.
APPLICATION GRANTED
23/00283/FUL – GABALFA
57 INGLEFIELD AVENUE, GABALFA, CARDIFF, CF14 3PY
Construction of dormer loft extension, and change of use to house of multiple occupation (sui generis class)
RESOLVED: to accept the report taking into considerations observations made by Cllr Ash-Edwards.
Members were advised that Scrutiny Chairs have agreed that a joint scrutiny task and finish group be established, consisting of the Chairs of the five Scrutiny Committees and two volunteers from each committee. The Task group needs to be established as soon as possible to plan work around the RLDP Preferred Strategy, scheduled to go out to consultation in July 2023.The Task and Finish Group will establish the Terms of Reference itself. And, following approval of the Preferred Strategy, it is anticipated that the group will continue to meet periodically, to undertake scrutiny of future stages of the Replacement LDP.
The Chairperson sought expressions of interest in joining this task group.
RESOLVED: that Cllrs Hunt, Henshaw, Chowdhury and Thomson expressed interest in joining the task group.
Members noted the correspondence between committee and the Cabinet.
RESOLVED: Pursuant to this Committee’s delegated powers the following development control applications be determined in accordance with the recommendation set out in the reports of the Director of Planning, Transport and Environment, subject to any further amendments as detailed below and notification be given of the decisions in accordance with Section 70 of the Town and Country Planning Act 1990 or Section 74 of the Planning (Listed Building & Conservation) Act 1990.
APPLICATIONS GRANTED
22/02644/DOC – WHITCHURCH AND TONGWYNLAIS
LAND TO THE NORTH-WEST OF WHITCHURCH HOSPITAL PLAYING FIELDS.
Discharge of Condition 16 (GIMS) of 17/01735/MJR
22/02231/RES – WHITCHURCH AND TONGWYNLAIS
LAND TO THE NORTH-WEST OF WHITCHURCH HOSPITAL PLAYING FIELDS
Application for the approval of Reserved Matters pursuant to Outline Planning Permission reference 17/01735/MJR for the delivery of the new Velindre Cancer Centre, parking, landscaping works, pedestrian infrastructure and all other ancillary works.
22/026434 – WHITCHURCH AND TONGWYNLAIS
LAND TO THE NORTH-WEST OF WHITCHURCH HOSPITAL PLAYING FIELDS
Discharge of Conditions 17 (CEMP) of 17/01735/MJR
RESOLVED: Pursuant to this Committee’s delegated powers the following development control applications be determined in accordance with the recommendation set out in the reports of the Director of Planning, Transport and Environment, subject to any further amendments as detailed below and notification be given of the decisions in accordance with Section 70 of the Town and Country Planning Act 1990 or Section 74 of the Planning (Listed Building & Conservation) Act 1990.
APPLICATIONS GRANTED
22/02542/VAR – HEATH
32 ANTONY ROAD
Variation of Condition 3 of 20/01075/MNR, to extend trading hours Wednesday to Saturday from 19:00 to 21:00.
Approved as per recommendation in addition to amendment to wording of Condition 3 and additional Condition 7 as below :
3) For a temporary period of 12 months from the date of the permission hereby granted, Members of the public shall only be admitted to or allowed to remain on the premises between the hours of 07:00 and 19:00 on Mondays and Tuesdays, 07:00 and 21:00 on Wednesdays to Saturdays, and 08:00 and 17:00 on Sundays, following which members of the public shall only be admitted to or allowed to remain on the premises between the hours of 07:00 and 19:00 on Mondays to Saturdays, and 08:00 and 17:00 on Sundays.
7) After 19:00 on any day, no external seating / tables shall be sited or allowed to remain within the site curtilage, other than within the area outlined in blue on the external seating plan dated 02/02/2023.
22/02170/REM – GRANGETOWN
TRAMSHED, PENDYRIS STREET
Removal of Condition 1 of 21/01813/MJR to enable permanent permission for late night events.
22/02308/FUL – SPLOTT
LAND OFF LEWIS ROAD
Demolition of buildings, removal of hardstanding areas, reprofiling of site and associated works.
Subject to the following:
Approved as per recommendation, subject to removal of recommended condition 5 (with all subsequent conditions re-numbered).
22/02949/WTTPP – PENTYRCH AND ST FAGANS
WOODLAND ADJOINING MAIN ROAD, GWAELOD-Y-GARTH
Completion of works to woodland path, provision of porous surfacing with no-dig construction where the new permanent path surfacing yet to be constructed would be in excess of 20% of currently unsurfaced ground within a Root Protection Area.
22/02867/HSE – WHITCHURCH AND TONGWYNLAIS
1 CLAS ISAN
Hip to gable and rear dormer roof extensions.
APPLICATIONS RESOLVED TO BE GRANTED SUBJECT TO ENTERING INTO A BINDING SECTION 106 AGREEMENT
22/01718/MJR – SPLOTT
MORRLAND ROAD, DAY CENTRE, MOORLAND ROAD
Demolition of the existing moorland Community Centre and the proposed development of 13 independent living flats for the older persons, community facility and associated works.
22/0220/FUL – BUTETOWN
MERCHANT PLACE AND CORYS BUILDINGS, 3 BUTE PLACE AND 57 BUTE STREET
Partial demolition of existing buildings and the redevelopment of the site to provide an educational facility, including the restoration of the existing buildings, internal and external alterations to the existing buildings, the erection of an 8-storey building, ancillary cycle parking, landscaping, public realm improvements and associated works.
22/02204/LBC – BUTETOWN
MERCHANT PLACE AND CORYS BUILDINGS, 3 BUTE PLACE AND 57 BUTE STREET.
Partial demolition of existing buildings and the redevelopment of the site to provide an educational facility, including the restoration of the existing buildings, internal and external alterations to the existing buildings, the erection of an 8-storey building, ancillary cycle parking, landscaping, public realm improvements and associated works.
Listed Building Consent.
RESOLVED: that
1) Approval be given to the disposal strategy as set out in this report in line with the independent advice attached at Confidential Appendix 2 and authority be delegated to the Director of Economic Development in consultation with the Cabinet Member for Investment and Development, the Section 151 Officer and the Legal Officer to develop detailed heads of terms to be approved at a future meeting of Cabinet.
2) Approval be given to the preferred operator for the proposed new Velodrome facility at the International Sports Village as set out in Confidential Appendix 5 subject to the detailed due diligence set out in this report and authority be given to the development of a Full Business Case for the whole leisure destination including associated infrastructure in line with the costs set out in Confidential Appendix 10 and as part of this authority be provided to identify an appropriate operator for the Closed Loop Circuit.
3) Approval be given to the preferred operator for the Ice Arena as set out in Confidential Appendix 5 including the proposal for the family attraction as set out in this report and illustrated in Confidential Appendix 6, and authority be delegated to the Director of Economic Development in consultation with the Cabinet Member for Investment and Development, the Section 151 Officer and the Legal Officer to conclude suitable legal and commercial terms in line with the criteria set out in this report.
4) the Strategic Outline Case for the Energy Strategy for the International Sports Village attached as Confidential Appendix 12 be noted and approval be given to the development of an Outline Business Case to be presented back to a future meeting of Cabinet.
5) Approval in principle be given to the proposal to establish a single management organisation for the leisure destination at the International Sports Village and authority be given to the preparation of an Outline Business Case in line with the strategy set out in this report and Confidential Appendices 5, 7 and 8.
6) Approval be given to the development of an Outline Business Case to consider the options for delivery of the proposed Multi Storey Car Park including an agreement in principle to the introduction of an appropriate charging regime to be approved as part of a Full Business Case to be presented to a future meeting of Cabinet.
7) Approval be given to the budgetary spend set out at Confidential Appendix 13 to enable the development of the various Business Cases proposed in this report and to enable the submission of planning applications as required.
RESOLVED: Pursuant to this Committee’s delegated powers the following development control applications be determined in accordance with the recommendation set out in the reports of the Director of Planning, Transport and Environment, subject to any further amendments as detailed below and notification be given of the decisions in accordance with Section 70 of the Town and Country Planning Act 1990 or Section 74 of the Planning (Listed Building & Conservation) Act 1990.
APPLICATIONS GRANTED
22/02280/FUL – WHITCHURCH AND TONGWYNLAIS
WHITCHURCH HOSPITAL, PARK ROAD
Temporary construction access route to the site of the approved Velindre Cancer Centre. The north-south connecting section is then proposed to be converted to provide a revised emergency access for approved Velindre Cancer Centre.
That planning permission be GRANTED subject to the Local Planning Authority receiving a confirmation letter from the Welsh Ministers that the decision has not been called in, and authorises the Local Planning Authority to grant planning permission pursuant to its Direction dated 12th January 2023 made under Article 18 of the Town and Country Planning (Development Management Procedure)(Wales) Order 2012
Subject to an amendment to Condition 1 to read:
‘All vehicular use of the temporary road hereby approved shall cases by no later than 30 November 2026, and thereafter by no later than 30 January 2027 (or prior to the first beneficial use of the new Cancer Care Hospital whichever comes first) the width of the road shall have been reduced and remaining land restored/landscaped in accordance with the approved Landscape plan reference 70066877-WSP-EV-DR-LA-P1-5101 REV PO1 and the general arrangement/ details approved under condition 3. The access shall thereafter be retained in its approved form.
APPLICATIONS DEFERRED
22/02542/VAR – HEATH
32 ST ANTHONY ROAD
Variation of Condition 3 of 20/01075/MNR to extend trading hours Wednesday to Saturday from 19:00 to 21:00
REASON: In order for a site visit to the location to take place.
22/02184/OUT – CAERAU
LAND TO THE SOUTH WEST OF PARK VIEW HEALTH CENTRE ADJACENT TO ELY AND CAERAU COMMUNITY HUB, TRESEDER WAY
Proposed Health and Wellbeing Hub and associated infrastructure works relating to access, parking, drainage and landscape.
REASON: In order for a site visit to the location to take place.
RESOLVED: Pursuant to this Committee’s delegated powers the following development control applications be determined in accordance with the recommendation set out in the reports of the Director of Planning, Transport and Environment, subject to any further amendments as detailed below and notification be given of the decisions in accordance with Section 70 of the Town and Country Planning Act 1990 or Section 74 of the Planning (Listed Building & Conservation) Act 1990.
APPLICATIONS GRANTED
20/01882/MJR – LLANDAFF
WINDRUSH, 58 PWLLMELIN ROAD
Councillor Michael left the room for consideration of this item in accordance with his prejudicial interest.
Demolition of existing dwelling house and replacement with 23 self-contained residential apartments, contained within four separate blocks with landscaping, access, parking and associate infrastructure.
22/01717/MJR – GRANGETOWN
INTERNATIONAL SPORTS VILLAGE
Councillor Robson left the room for consideration of this item in accordance with his prejudicial interest.
Variation of Condition 2 of 21/02848/MJR to amend the list of approved plans to substitute with the amended plans.
21/02138/MJR – SPLOTT/RUMNEY
CARDIFF COASTAL FLOOD DEFENCES. THE SEVERN ESTUARY COASLINE AND EAST AND WEST BANKS OF THE RIVER RHYMNEY, CARDIFF
Councillor Michael left the room for consideration of this item in accordance with his prejudicial interest.
The Construction of a series of Fluvial and Coastal Flood Defences along the Severn Estuary Coastline and East and West banks of the River Rhymney, to include Rock Armour Revetments, Concrete Erosion Protection Mats, Earth Bunds a Double Flood Gate (at the Rhymney River Motor Boat Sail & Angling Club) and Sheet Piling.
Subject to the following amendments to Condition 5:
No development, including site clearance, shall commence until a Construction Environmental Management Plan (CEMP) has been submitted to and approved in writing by the Local Planning Authority.
The CEMP shall include details of:
• Construction methods: details of materials, sediment management measures (including if contaminated sediment present); how waste generated will be managed; linked to Construction Method Statement and Contaminated Sediment Sampling Plan or Strategy (subject to separate conditions)
• General Site Management: the construction programme including phasing of development, construction timetable, details of site clearance; details of site construction drainage, containments areas, appropriately sized buffer zones between storage areas (of spoil, oils, fuels, concrete mixing and washing areas) and any watercourse or surface drain, piling type and timings; vehicle access routes over sensitive habitats e.g. saltmarsh and associated protection measures; contaminated sediment plan and strategy.
• Biodiversity Management: details of piling restrictions to avoid disturbance to migratory fish and the fish assemblage; details of saltmarsh habitat protection; measures to avoid disturbance to overwintering and ground nesting birds; invasive species management including link to biosecurity risk assessment and management plan; measures to protect otter and badger during construction and avoidance measures for foraging and commuting bats; Precautionary Working Method Statement for amphibians and reptiles; other species and habitats protection, avoidance and mitigation measures (to include breeding birds, bats, dormouse, water vole and invertebrates). To be informed by update and pre-construction surveys as necessary.
• Soil and Sediment Management: details of topsoil strip, sediment removal, storage and amelioration for re-use. Link to contaminated sediment plan and strategy.
• Measures to ensure new bunds will naturally regenerate or if seeded, the use of locally sourced seeds.
• Control of Nuisances: details of restrictions to be applied during construction including timing, duration and frequency of works; details of measures to minimise noise and vibration including piling activities, for example acoustic barriers; details of dust control measures; measures to control light spill and the conservation of dark skies;
• Resource Management: details of fuel and chemical storage and containment; details of waste generation and its management; details of sediment management; details of water consumption, wastewater and energy use.
• Traffic Management: details of site deliveries, plant on site, wheel washing facilities; site hoardings, dedicated vehicle access routes, construction staff parking, traffic management and habitat protection measures;
• Pollution Prevention: demonstrate how relevant Guidelines for Pollution Prevention and best practice will be implemented, including details of emergency spill procedures and incident response plan; details of how contaminated sediments will be dealt with.
• Details of the persons and bodies responsible for activities associated with the CEMP and emergency contact details.
• Contact details of the Community Liaison Officer who will communicate and coordinate between the construction contractor and local residents.
• Landscape/ecological clerk of works to ensure construction compliance with approved plans and environmental regulations;
• NVC maps to inform construction access routes and compound locations so to avoid sensitive places.
The CEMP shall be implemented as approved during the site preparation and construction phases of the development.
Reason: In the interests of highway safety, protection of the environment and public amenity in accordance with Local Development Plan Policies T5 (Managing Transport Impacts), T6 (Impact on Transport Networks and Services), EN5 (Designated Sites), EN6 (Ecological Networks and Features of Importance for Biodiversity), EN7 (Priority Habitats and Species), EN10 (Water Sensitive Design), and EN13 (Air, Noise, Light Pollution and Land Contamination)”
APPLICATIONS REFUSED
22/011636/MNR – RHIWBINA
LAND TO THE REAR OF CANOLFAN GARDEN AND SHEDS BETWEEN 238 PANTBACH ROAD AND HEOL Y BONT.
Councillor Robson reaffirmed his prejudicial interest and confirmed he would be speaking as a Ward Councillor.
Retention of storage container for Snails Deli.
REASON:
1. The industrial appearance of the storage container, including its scale, form and materials and it’s siting forward of the building line to Heol Y Bont, are out of keeping with the residential character, quality and pattern of development in the surrounding area, resulting in an insensitive and obtrusive feature in the street scene which is detrimental to visual amenity and the character of the area, contrary to policy KP5 (i) of the Cardiff Local Development Plan.
2. The storage container, by virtue of its scale, form, material, siting forward of the building line to Heol Y Bont and projection above the adjacent boundary wall, is unneighbourly and detrimental to the amenities of residents of 1 Heol Y Bont in that it is unsightly and obtrusive when viewed from that property, contrary to policy KP5(x) of the Cardiff Local Development Plan.
3. That the Chief Legal and Democratic Services Officer be authorised to issue an Enforcement Notice under Section 172 of the Town and Country Planning Act 1990 to secure the removal of the unauthorised storage container.
22/01707/MNR – SPLOTT
88 SPLOTT ROAD
Councillor Stubbs left the room for consideration of this item in accordance with his prejudicial interest. Councillor Irene Humphreys chaired this item.
Ground floor rear extension, dormer loft conversion, alterations and change of use to use to large SUI Generis house in multiple occupation.
Subject to the following:
Amendment to Condition 5 to read:
The development shall be carried in accordance with the following approved plans.
· CXB3/4/a/b/c/d – Proposed Ground Floor Plan
· CXB3/5/a – Proposed First and Second Floor Plan
· CXB3/6/a/b/c – Proposed Elevations
REASON: To ensure satisfactory completion of the development and for the avoidance of doubt in line with the aims of Planning Policy Wales to promote an efficient planning system.
REASON:
“By virtue of the alterations required to facilitate the use of the property as a house in Multiple Occupation the proposal will provide an insufficient amount of useable amenity space to serve the number of occupiers contrary to Policy KP5: Good Quality and Sustainable Design and Policy H5: Sub-Division or Conversion of Residential Properties of the Cardiff Local Development Plan and the advice contained within the House in Multiple Occupation Supplementary Planning Guidance 2016.
APPLICATIONS DEFERRED
2/01718/MJR - SPLOTT
Moorland road day centre, Moorland Road
RESOLVED – That the Chairperson writes to the Cabinet Member on behalf of the Committee to convey any comments, observations and recommendations made during the way forward.
RESOLVED: that the response to the recommendations of the Environmental Scrutiny Committee Joint Task and Finish Group on the Replacement Local Development Plan – Strategic and Delivery Options, as set out in appendix 2 be approved
RESOLVED: Pursuant to this Committee’s delegated powers the following development control applications be determined in accordance with the recommendation set out in the reports of the Director of Planning, Transport and Environment, subject to any further amendments as detailed below and notification be given of the decisions in accordance with Section 70 of the Town and Country Planning Act 1990 or Section 74 of the Planning (Listed Building & Conservation) Act 1990.
APPLIATIONS GRANTED
Councillor Adrian Robson, in accordance with his prejudicial interest, left the meeting during consideration of this item.
21/02608/MNR – LLANDAFF NORTH
LAND AT EITHER SIDE OF RIVER TAFF COMPRISING LAND SOUTH OF EXISTING ACCESS ROAD WITHIN HAILEY PARK AND LAND AT EASTERN TURNING HEAD OF DE BRAOSE CLOSE, DANESCOURT.
The Construction of Sewerage Pumping Station and Associated Compound Within Hailey Park Connecting to the Existing Gated Hard Standing Access Road Including Internal Kiosk Units With Security Fencing and Landscape Planting to the Eastern, Western and Southern Boundaries to Prevent Landscape Impacts on Hailey Park. The De Braose Close Development Would Include a 1.2m Tall Actuation Valve Kiosk Upon Overgrown Scrubland Adjacent to the Eastern Pedestrian Footway.
Councillor Adrian Robson, in accordance with his prejudicial interest, left the meeting during consideration of this item.
22/00347/MJR – RADYR
PLASDWR, NORTH WEST CARDIFF
Re-discharge of Condition 24 (strategic foul drainage masterplan) of outline planning permission 14/02733/MJR (condition 24 previously discharged under application 19/02887/MJR).
APPLICATIONS REFUSED
18/00736/MNR – WHITCHURCH & TONGWYNLAIS
71 CHURCH ROAD
Proposed demolition of existing garage / outbuilding construction of new 2 storey detached dwelling, detached replacement garage with studio above and glazed link to existing dwelling
REASON:
This application was considered on 6th July 20122 Planning Committee where it was resolved to defer the application to the next meeting of Planning Committee for reasons for refusal. The application was refused for the following reasons:
1. The proposed layout makes insufficient provision for replacement planting in mitigation for the removal of existing vegetation / boundary planting to the detriment of the character of the Church Road Conservation Area contrary to Policies 5 KP5: Good Quality and Sustainable Design and EN9: Conservation of the Historic Environment of the Adopted Cardiff Local Development Plan.
2. The proposed dwelling would be likely to have a dominating and overbearing impact on the living conditions of the occupiers of No. 1 Wingfield Road by virtue of its scale and close proximity to the boundary with this property. As such, the proposal would be contrary to advice contained in Policy KP5: Good Quality and Sustainable Design of the Cardiff Local Development Plan and paragraph 4.11 of the Cardiff Infill Sites Supplementary Guidance (November 2017).
RESOLVED: Pursuant to this Committee’s delegated powers the following development control applications be determined in accordance with the recommendation set out in the reports of the Director of Planning, Transport and Environment, subject to any further amendments as detailed below and notification be given of the decisions in accordance with Section 70 of the Town and Country Planning Act 1990 or Section 74 of the Planning (Listed Building & Conservation) Act 1990.
APPLICATIONS GRANTED:
22/00725/MJR – WHITCHURCH & TONGWYNLAIS
LAND TO THE NORTH-WEST OF WHITCHURCH HOSPITAL PLAYING FIELDS
Discharge of Condition 8 (Construction Environmental Management Plan) & 10 (Mitigation and Monitoring) of 20/01110/MJR
Subject to the following note:
“Members expressed their view that hours of working should be limited to the specified hours, albeit noting that any works undertaken beyond agreed operating hours would require the consent of the Local Planning Authority and Shared Regulatory Services”
22/00802/MJR – WHITCHURCH & TONGWYNLAIS
LAND TO THE NORTH-WEST OF WHITCHURCH HOSPITAL PLAYING FIELDS.
Discharge of Condition 17 (Construction Environmental Management Plan) of 17/01735/MJR
Subject to the following note:
“Members expressed their view that hours of working should be limited to the specified hours, albeit noting that any works undertaken beyond agreed operating hours would require the consent of the Local Planning Authority and Shared Regulatory Services”
22/00711/MNR – SPLOTT
100 SPLOTT ROAD
Ground floor extension, rear dormer and alterations to create a 7 Bedroom sui generis house in multiple occupation.
APPLICATIONS REFUSED
22/00885/MNR – CATHAYS
76 MAINDY ROAD
Change of use from a C3 dwelling house to eight person house of multiple occupation (sui generis) with ground and first floor rear extensions, rear dormer roof extension, insertion of roof light to the front roof plane and associated alterations
REASON: The use of the property as an 8 bedroom House in Multiple Occupation has the potential to further exacerbate the unacceptable cumulative adverse impacts on the amenities of the area by virtue of:
§ a higher number of transient residents leading towards less community cohesion and undermining the objectives of securing a sustainable mixed use community, contrary to Policy KP5, Policy KP13 and Policy H5 of the Cardiff Local Development Plan (2006-2016) and advice contained within the Houses in Multiple Occupation Supplementary Planning Guidance (2016).
§ a higher portion of transient residents leading to an increase of cumulative demand on social, community and physical infrastructure, contrary to Policy KP5, Policy KP13 and Policy H5 of the Cardiff Local Development Plan (2006-2026) and advice contained within the Houses in Multiple Occupation Supplementary Planning Guidance (2016).
1. The use of the property as an 8 bedroom HMO will result in an increase in the number of HMO’s within the vicinity to the detriment of the existing community affecting its composition, cohesion, character, functionality and its sense of place contrary to Policy KP5, Policy KP13 and Policy H5 of the Cardiff Local Development Plan (2006-2026) and the Houses in Multiple Occupation Supplementary Planning Guidance (2016).
APPLICATIONS DEFERRED
18/00736/MNR – WHITCHURCH & TONGWYNLAIS
71 CHURCH ROAD
Proposed demolition of existing garage/ outbuilding construction of new 2 storey detached dwelling, detached replacement garage with studio above and glazed link to existing dwelling.
REASON: As a result of a technical issue with the new software system and Councillors being unable to speak.
RESOLVED: that the Environmental Scrutiny Task & Finish Letter on the Replacement Local Development Plan Strategic and Delivery Options be received and a response provided within two cycles.
RESOLVED: Pursuant to this Committee’s delegated powers the following development control applications be determined in accordance with the recommendation set out in the reports of the Director of Planning, Transport and Environment, subject to any further amendments as detailed below and notification be given of the decisions in accordance with Section 70 of the Town and Country Planning Act 1990 or Section 74 of the Planning (Listed Building & Conservation) Act 1990.
APPLICATIONS RESOLVED TO BE GRANTED SUBJECT TO ENTERING INTO A BINDING SECTION 106 AGREEMENT
21/02883/MJR – BUTETOWN
PHASE 2, PLOT 1 CENTRAL QUAY AT FORMER BREWERY SITE CRAWSHAY STREET.
Full planning application for a mixed-use building providing commercial uses at ground floor/mezzanine level (use classes A1/A2/A3/B1/D1/D2) and residential development above (use Class C3), is landscaping including a new public square (Chimney Square) associated car and cycle parking, access, drainage and other infrastructure works required for the delivery of central quay (phase 2, plot 1)
Subject to the following amendment to paragraph 3.11 to read.
’1 car parking spaces are proposed, which will be allocated to residential units, 3 of which are designated disabled parking bays. The car park is situated to the north-east of the site and will be accessed using a rear service lane, with a turning head to the north-eastern corner. This will then lead to the part two-way vehicle route of the boulevard, connecting to the existing Crawshay Street access’
Subject to the following amendment to paragraph 9.43 to read:
‘The proposed residential units are considered a reasonable size and will receive sufficient levels of outlook and ventilation. The application proposes 78 balconies for the 402 units which equates to 25% of the overall units’
21/02884/MJR – BUTETOWN
PHASE 2, PLOT 1 CENTRAL QUAY AT FORMER BREWERY SITE CRAWSHAY STREET
Full planning application for a mixed-use building providing commercial uses at ground floor/mezzanine level (use classes A1/A2/A3/B1/D1/D2) and residential development above (use Class C3), is landscaping including a new public square (Chimney Square) associated car and cycle parking, access, drainage and other infrastructure works required for the delivery of central quay (phase 2, plot 2)
Subject to the following amendment to paragraph 10.46 to read:
‘The proposed residential units are considered a reasonable size and will receive sufficient levels of outlook and ventilation. The application proposes 59 balconies for the 316 units which equates to 19% of the overall units’
APPLICATIONS DEFERRED
22/00475/MJR – WHITCHURCH/TONGWYNLAIS
ENTRANCE TO WHITCHURCH HOSPITAL/PARK ROAD
Discharge of Condition 9 (Scheme of Highway works to park road and the Whitchurch Hospital entrance of 20/20110/MHJ
REASON: In order for a site visit to take place.
18/00736/MNR – WHITCHURCH/TONGWYNLAIS
71 CHURCH ROAD
Proposed demolition of existing garage/outbuilding construction of new 3 storey detached dwelling, detached replacement garage with studio above and glazed link to existing dwelling.
REASON: In order for a site visit to take place.