FORESTRY COMMISSION WALES LAND, AND AGRICULTURAL LAND SOUTH OF RHYDCYMERAU (B4337) AND NORTH OF ABERGORLECH (B4310)
PROPOSED ERECTION OF TWELVE (12) WIND TURBINES TO FORM A SCHEME KNOWN AS 'BRECHFA FOREST EAST WIND FARM'. THE PROPOSAL WILL ALSO INCLUDE NEW TRACKS, UPGRADE OF EXISTING TRACKS, ANEMOMETRY MAST, SUBSTATION, BORROW PIT AND OTHER ASSOCIATED DEVELOPMENT. THE DEVELOPMENT WILL INVOLVE THE FELLING OF TREES
- Status
- Approved
- Reference
- E/24195
- Type
- Full planning permission
- Size
- Medium
- Ward
- Cynwyl Gaeo (Historic)
- Received
- 7 January 2011
- Consultation date
- 26 December 2013
- Decided
- 22 October 2014
- Decision
- Full Granted
Have your say
A decision has been made, so the council is no longer taking comments. Approved, 22 October 2014.
Where it has got to
Application received
The council checks the application is complete and gives it a reference number.
Consultation
The council tells neighbours and others, usually with a site notice or letters. Anyone can comment, usually within 21 days.
Decision
Most applications are decided by the council's planning officers. Larger or disputed ones go to the planning committee, where councillors decide in public.
After the decision
If permission is refused, the applicant can appeal to Planning and Environment Decisions Wales. Other people can't appeal, but can comment on an appeal.